| Block/ Project | Date | Sheet Type | Sheet # | Sheet | Drawing Kind | Drawing Type | Size | Drawing Name/Description | Notes | |
| 159R | 06/01/91 | 1of1 | A | SEAS & Annex Computer Cabling | ||||||
| 159R | 03/18/92 | 1of1 | A | SEAS Annex Revisions | ||||||
| 159R | 11/11/76 | R-01 | D | Remodel Dining Room Regional Research Institute | Wall Section & Elevations, Power/Lighting/Telephone | |||||
| 159R | 03/10/77 | R-02 | A | Room 256 | ||||||
| 159R | 03/18/77 | R-03 | D | 2nd Floor Ceiling Remodel | Ceiling & Lighting Plans: 2nd Floor Lobby & North Corridor | |||||
| 159R | 04/28/78 | R-04 | A | Reception Lobby for RRI, V120 | ||||||
| 159R | 11/01/78 | R-05 | D | Remodel of Ondine Kitchen | Area Floor Plan, Study Desks | |||||
| 159R | 03/24/80 | R-06 | B | Toilet Room 102, Handicapped Facility | ||||||
| 159R | 03/18/76 | R-07 | A | New Mailroom Lobby | ||||||
| 159R | 01/02/80 | R-08 | A | Fifth Avenue Ramp to Lower Level Parking | ||||||
| 159R | 08/07/90 | R-09 | A | Handicap Door Remodel, 1st Floor | ||||||
| 159R | 01/04/80 | R-10 | D | Handicapped Access Ramp Plan Elevation | East Elevation with New Access Ramp | |||||
| 159R | 03/04/80 | R-10A | D | Handicapped Access Ramp Plan, Location Plan, East | ||||||
| 159R | 04/05/83 | R-11 | B | Door Replacement, Ondine | Door Elevation, Additional Hardware Notes | |||||
| 159R | 07/05/83 | R-12 | A | Room 251 Remodel | Administrative Systems | |||||
| 159R | 08/10/83 | R-13 | A | Exterior Waterproofing, Parapet/Roof Deck Detail | ||||||
| 159R | 08/10/83 | R-14 | A | Exterior Waterproofing Partial North Elevation Hall Street | ||||||
| 159R | 07/05/83 | R-15 | A | Existing Partitions Room 250 | ||||||
| 159R | 01/11/84 | R-16 | A | Door Replacement at North Stair Tower, Ground Floor | General Notes, Demountable Fin Detail, Elevation of New Door & Lite | |||||
| 159R | 08/29/84 | R-17 | C | Remodel Room 260 | ||||||
| 159R | 12/03/84 | R-18 | B | Room 64 Ondine Remodel | Base Cabinet, Faucet, New Panel Feed | |||||
| 159R | 12/03/84 | R-19 | D | Existing Partitions Room 250 | Key for Schedule of Work | |||||
| 159R | 05/19/86 | R-20 | D | Remodel Ground Floor Classrooms in the Ondine 54 & 62 | North, South, East & West Elevations | |||||
| 159R | R-21 | D | Ondine Exterior Painting | Floor Plan, Drawing Index | ||||||
| 159R | R-21B | D | SEAS Annex Remodel For New Solid State Laboratory "A-1" | Room Finish & Door Schedules. Head, Jamb, Concealed Mullion, Sill, New Partition & Wall Details | ||||||
| 159R | R-21C | D | SEAS Annex Remodel For New Solid State Laboratory "A-2" | Reflected Ceiling Plan, Existing Wall 1 Hour Upgrade "A-3" | ||||||
| 159R | R-21D | D | SEAS Annex Proposed Remodel L50, C50, 72B & 72C | |||||||
| 159R | 01/14/88 | R-21E | D | SEAS Annex Remodel For Solid State Laboratory Mechanical Plan | ||||||
| 159R | 10/15/87 | R-20 | B | SEAS Annex Remodel For Solid State Laboratory Mechanical Plan | ||||||
| 159R | 10/15/87 | R-22A | B | Front Entry For SEAS Solid State Laboratory | Elevation, Floor Plan, Door & Frame Colors | |||||
| 159R | 10/15/87 | R-22B | B | Front Entry For SEAS Solid State Laboratory | Head, Jamb, Concealed Mullion & Sill Addenda 11/12/87 | |||||
| 159R | 07/17/90 | R-23-A1 | D | Remodel Room 250 Regional Research Institute | Construction Notes, Floor Plan, Detail, Reflected Ceiling Plan | |||||
| 159R | R-23-E1 | D | Remodel Room 250 Regional Research Institute | Demolition, Lighting, One Line Diagram, Power, Luminate Schedule | ||||||
| 159R | 07/17/90 | R-23-M1 | D | Remodel Room 250 Regional Research Institute | HVAC Floor Plan, Phase I & II. Supply Diffuser/Return Grille Plenum Detail,Roof Curb Detail & Equipment Schedule | |||||
| 159R | 10/30/91 | R-24 | D | SEAS Annex Remodel 54, 62, 64, 72 & Etcetera Demolition Plan | ||||||
| 159R | 10/30/91 | R-25 | D | SEAS Annex Remodel Lighting Plan | Construction Notes, Plumbing, Electrical, Existing Reflected Ceiling Plan | |||||
| 159R | 10/30/91 | R-26 | Architectural | D | SEAS Annex Remodel Plans & Excavations | |||||
| 159R | 10/30/91 | R-27 | Electrical | D | SEAS Annex Remodel Plans & Elevations 54A, 54B, 54C, 67, 68 & 70 | |||||
| 159R | 10/30/91 | R-28 | Mechanical | D | SEAS Annex Remodel Plans Elevations & Details | Demolition, Lobby Plan, Jamb Opening, Column Head, Door Detail, Exterior Elevation | ||||
| 159R | 03/10/92 | R-29 | B | SEAS Annex Remodel #1 Door Revision 60 | Demolition & Revised Floor Plan | |||||
| 159R | 03/10/92 | R-30 | B | SEAS Annex Area #1 Revsions - Missing | ||||||
| 159R | 09/10/92 | R-31 | A | Room 252 Layout | Door to be Added, Reinstall A.C. Unit, New Outlets | |||||
| 159R | 09/10/92 | R-32 | A | Plan Room 252 | ||||||
| 159R | 08/21/92 | R-33 | A | Option #1 - Floors 6-12 1 Bedroom Apartment - Missing | ||||||
| 159R | 08/22/92 | R-34 | A | Detail of ITFS Conduit | Floor Section Detail, Dow Corning "Fire-Stop" Sealant | |||||
| 159R | 07/27/94 | R-35 | E | Platform Lift Installation, Fifth Avenue Cinema (Bid Document) | Floor Plans, Elevations, Sections, Slab/Support Plan, Demolition & Construction Notes | |||||
| 159R | 08/02/94 | R-35A | E | Platform Lift Installation, Fifth Avenue Cinema (with Addendum) | Floor Plans, Elevations, Sections, Slab/Support Plan, Demolition & Construction Notes, Addendum | |||||
| 159R | 09/16/94 | R-36 | E | Room 204 Remodel (Handicap Modifications) | Demolition & Revised Floor Plans, Interior Elevations, Details, Notes | |||||
| 159R | 11/22/94 | R-37 | E | Send/Receive Site Room 54 Cover Sheet | Vicinity Map, First Floor Plan, Drawings Index, Abbreviations | |||||
| 159R | 11/23/94 | R-38 | E | Send/Receive Site Room 54 Plans | Demolition, Ceiling Demo, Construction Notes, Reflected Ceiling | |||||
| 159R | 11/23/94 | R-39 | E | Send/Receive Site Room 54 Details | Podium Plan, Sections & Elevations, TV Cabinet Section & Elevations, Copy Scan, Riser, Recessed Ceiling Mount, Table Anchor | |||||
| 159R | 11/24/92 | R-40 | B | SEAS Annex Room 54 AV Equipment Cabinet | Front Side, Plan Section | |||||
| 159R | 09/24/91 | R-41 | B | SEAS Annex Room 72 & 72A Remodel | Furniture Layout Plan | |||||
| 159R | 12/20/91 | R-42 | A | ED-NET Laser Bracket Location | Area of Work, Penthouse Roof | |||||
| 159R | 08/21/95 | R-43 | E | Cover Sheet | ||||||
| 159R | 08/21/95 | R-44 | E | Basement Floor Plan | ||||||
| 159R | 08/21/95 | R-45 | E | Reserved | ||||||
| 159R | 08/21/95 | R-46 | E | Reserved | ||||||
| 159R | 08/21/95 | R-47 | E | Reserved | ||||||
| 159R | 08/21/95 | R-48 | E | Reserved | ||||||
| 159R | 09/12/95 | R-49 | E | Reserved | ||||||
| 159R | 09/12/95 | R-50 | E | Reserved | ||||||
| 159R | 06/22/96 | R-51 | E | Parking Rehabilitation | Cover Sheet, Basement,First Floor,Vicinity Map | |||||
| 159R | 06/24/96 | R-52 | E | Parking Rehabilitation | Basement Floor Plan | |||||
| 159R | 06/27/96 | R-53 | E | Parking Rehabilitation | Disabled Parking Deck, First Floor Plan | |||||
| 159R | 04/24/00 | R-54 | E | Room 20/061 | MAT/SCI | |||||
| 159R | 08/15/00 | R-55 | B | Room 60 Remodel 2000 | ||||||
| 159R | 10/20/00 | R-56 | A | Telescope | ||||||
| Size Legend: A = 9"x12", B = 12"x18", C =18"x24", D = 24"x36", E = 30"x42", F= 36"x48" |