McDonald's (Sam's Hof Brau Conversion)
|
||||||||||
Consultants: Ruhl-Parr & Associates |
||||||||||
| Block/ Project | Date | Sheet Type | Sheet # | Sheet | Drawing Kind | Drawing Type | Size | Drawing Name/Description | Notes | |
| 160.03 | 04/22/96 | A1 | Architectural | D | Site Plan | Legal Description, Area of Project | ||||
| 160.03 | 04/22/96 | A2 | Architectural | D | Floor Plan/Exterior Modifications | City of Portland Revisions, Permit Set, Remove Existing Brick & Meta Stud Wall | ||||
| 160.03 | 04/23/96 | A3 | Architectural | D | Exterior Modifications, West & North Elevations | City of Portland Revisions, Permit Set, New Signage, New Aluminum Storefront Window System, New Half Door | ||||
| 160.03 | 04/22/96 | A4 | Architectural | D | Demolition Plan | Existing Construction to be Removed, Permit Set | ||||
| 160.03 | 05/01/96 | A5 | Architectural | D | Floor Plans | New Construction, Kitchen Coordination, Revisions, Permit Set | ||||
| 160.03 | 05/01/96 | A6 | Architectural | D | Schedules | Toilet/Kitchen Accessories Schedule, Room Finish Schedule, Counter Details, Men's & Women's Restroom, Door Hardware, Door Types, General Notes, Door Schedule, Toilet Room Back-up Supports | ||||
| 160.03 | 05/01/96 | A7 | Architectural | D | Reflected Ceiling Plan | Kitchen Coordination, Revisions, Permit Set, Grill Locations Revised, Patch Ceiling | ||||
| 160.03 | 05/01/96 | A8 | Architectural | D | Ceiling Details, Light Fixture Schedule | New Suspended Ceiling at Dining, Exhaust Duct Enclosure, Menu Board Valance, Runner Detail, Emergency/Exit Lighting, Lighting Schedule, Notes | ||||
| 160.03 | 05/01/96 | CO | D | Cover Sheet | General Notes, Drawing Index, Architectural, Mechanical, Electrical, Plumbing, Kitchen Equipment, Specifications | |||||
| 160.03 | 05/01/96 | E1 | Electrical | D | Electrical General Notes, Load Summary, Riser Diagram | Single Line Riser Diagram, Load Summary, General Notes | ||||
| 160.03 | 05/01/96 | E2 | Electrical | D | Lighting Plan & Notes | Lighting Plan, Lighting Schedule, Emergency/Exit Lighting, Notes | ||||
| 160.03 | 05/01/96 | E3 | Electrical | D | Power Plan & Notes | Power Plan, General Notes, Legend | ||||
| 160.03 | 05/01/96 | E4 | Electrical | D | Wiring Details | Exhaust Fan & Cooking Equipment, Interlock Wiring Detail, Panel P-2 Isolated Grounding Detail, Fryer Connection Diagram, Wiring Detail: T7300 Thermostat with Averaging Remote Sensors | ||||
| 160.03 | 05/01/96 | K1 | D | Kitchen Layout Plan, Cover Sheet | Design Criteria, Regular Menu, Breakfast Menu, Happy Meals, Value Meals, Fry Bagging Station, Overhead Freezer, Chicken Holding, Biscuit Holding, Freezer With Floor, Crew Lockers | |||||
| 160.03 | 05/01/96 | K2 | D | Kitchen Equipment Layout | Front Counter Detail Viewing From Kitchen Side, Section Of Sink, Compartment Sink Elevation, General Notes, Back-up Support Notes | |||||
| 160.03 | 04/12/96 | K3 | D | Kitchen Rough-In Layout | Rough-in Plan, Rough-in Notes, Plan Notes, Abbreviation Legend | |||||
| 160.03 | 04/12/96 | K4 | D | Fixture Connection Legend 1 | Description, Manufacturer, Installation Requirements & Remarks | |||||
| 160.03 | 04/12/96 | K5 | D | Fixture Connection Legend 2 | Description, Manufacturer, Installation Requirements & Remarks | |||||
| 160.03 | 05/01/96 | M1 | Mechanical | D | Mechanical HVAC Layout | Air Balance Schedule, Mechanical Symbols, Titus Diffuser & Grille Schedule | ||||
| 160.03 | 05/01/96 | MEP1 | Mechanical | D | Mechanical Electrical Roof Plan | Equipment Schedule, HVAC Unit Schedule, HVAC Grounding Detail, Mechanical Notes | ||||
| 160.03 | 05/01/96 | P1 | D | Plumbing Plans | Soda System Detail | |||||
| 160.03 | 05/01/96 | P2 | D | Plumbing Notes | Plumbing Contractor Rough-in Identification, Reference Notes By Others, General Notes | |||||
| 160.03 | 05/01/96 | P3 | D | Plumbing Details & Risers | Domestic Water Riser Diagram, Waste & Vent Riser Diagram, Riser Diagram Notes, Plumbing Vent Detail, Elbow Detail, Floor Sink Detail | |||||
| 160.03 | 05/01/96 | SA1 | Structural | D | Specifications, West Zone (Division 1) | Instructions to Contractor, General Conditions, Special Conditions, Coordination | ||||
| 160.03 | 05/01/96 | SA2 | Structural | D | Specifications, West Zone (Divisions 2-5) | Site Work, Concrete, Masonry, Metals | ||||
| 160.03 | 05/01/96 | SA3 | Structural | D | Specifications, West Zone - Washington/Oregon (Divisions 5-7) | Metals Continued, Wood, Thermal & Moisture Protection | ||||
| 160.03 | 05/01/96 | SA4 | Structural | D | Specifications, West Zone (Divisions 7-9) | Doors & Windows, Finishes | ||||
| 160.03 | 05/01/96 | SA5 | Structural | D | Specifications, West Zone (Divisions 9-15) | Finishes Continued, Plumbing & Mechanical | ||||
| 160.03 | 05/01/96 | SA6 | Structural | D | Specifications, West Zone (Division 15) | Plumbing Continued | ||||
| 160.03 | 05/01/96 | SA7 | Structural | D | Specifications, West Zone (Divisions 15-16) | Plumbing Continued, Electrical | ||||
| 160.03 | 05/01/96 | SA8 | Structural | D | Specifications, West Zone (Division 16) | Electrical Continued | ||||
| 160.03 | 05/01/96 | SA9 | Structural | D | Specifications, West Zone - California | Security Openings, Fire Department Notes, Energy Notes, Handicap Notes, Handicap Details, Handicap Ramp Details, Health Department Notes | ||||
| Size Legend: A = 8.5" x 11", B = , C =, D = 24" x 36", E = 30" x 42" |