201.05R 03/11/68   R-01       A Extruded Aluminum Frame  
201.05R 03/13/68   R-02       A Head  
201.05R 08/03/68   R-03       A Revised Partial Plan Rooms 43, 44, 45 Anthropolgy, Osteology, Special Purpose Classroom, Anthro-Serology Lab
201.05R 08/05/6   R-04       A Project Sign "State Hall Additions"
201.05R 09/25/68   R-05       A Platform At Mechanical Shaft Plan & Section
201.05R 10/23/68   R-06       A Basement Reflected Ceiling Plan B11, B12, B13 & B14
201.05R 11/04/68   R-07       A Additional Lab Furniture, Room B13 Earth Science Cartology & General Geology, Relocate Door
201.05R 11/21/68   R-08       A Window Head At West Balcony, Fifth Floor Clarification Drawing
201.05R 11/27/68   R-09       A Toilet Accessories Locations Plan & Elevations. Napkin Disposal, Seat Cover Dispenser, Shelf
201.05R 11/27/68   R-09A       A Handicapped Toilet Accessories Elevations, Grab Rail
201.05R 12/07/68   R-10A       A Revision To Darkroom 390 Balance SHeet, Shelf Standards, Enlarger Location
201.05R 12/07/68   R-10B       A Revision To Darkroom 408  
201.05R 12/10/68   R-11       A Revision To Economics Department Offices 247 & 249  
201.05R 12/16/68   R-12       A Revision To Offices 320 & 322 Delete Door, Partition, Bookshelves
201.05R 03/19/69   R-13       A Revision To Rooms 276A, 278A & 285 Small Groups Experimental Lab Room. Relocated Doors, Camera
201.05R 03/20/69   R-14       A Mechanical Vent Curb  
201.05R 03/22/69   R-15       A Ceiling Recess At Room 415 Advanced Cartography: Partial Ceiling Plan, Section
201.05R 04/15/69   R-16       A Wicket Door At Reception Counter, Room 249 Plan, Section At Counter
201.05R 04/15/69   R-17       A Additional Door At South Wall, Room 502 Head
201.05R 04/15/69   R-18       A Wall Revision For Damper Access Panel, Fourth Floor Elevation, Wall Base At Access Pane
201.05R 04/21/69   R-19       A Stairway To Elevated Mechanical Room; Relocation & Addition To Landing Elevation & Plan
201.05R 04/15/69   R-20       A Revision of Wall To Expand Area W/Acousitc Treatment Room 275 Head & Acoustic Trim, S & W Walls, Panel At Ceiling
201.05R 04/02/69   R-21       A Steel Stairway To Penthouse Roof Connect Stringer To Landing, Connections & Landing Support, Base Plate
201.05R 05/02/69   R-22       A Office Unit Revision Section, Partial Elevation, Detail At Wall
201.05R 05/13/69   R-23       A Existing Exhaust Pit Extension AA Section, Elevator Shaft & Existing Stack
201.05R 05/20/69   R-24       A Ceiling At Corner Window Room 410 Head & Dropped Ceiling Assembly
201.05R 11/12/69   R-26       A Pass Door, Office 352 & 354 Elevation From 352, Head, Sill
201.05R 01/13/70   R-30       A Revised Transom Sill Metal Stops At Transom
201.05R 01/29/70   R-31       A Parapet Railing Penthouse Roof Plan, Section
201.05R 03/13/70   R-32       A Fireman's Ladder Support Plan, Section
201.05R 08/22/68   RE-01       A Partial Ground Floor Plan Lighting Revisions 43, 44, 45, 46 & 47  
201.05R 08/22/68   RE-01A       A Partial Ground Floor Plan Power & Signal Revisions 43, 44, 45, 46 & 47  
201.05R 10/10/68   RE-02       A Relocate Lighting At West Stair West Stair Ground & Basement Floors
201.05R 11/04/68   RE-03       A Control For Pump At Well #3  
201.05R 11/04/68   RE-04       A Control For Pump At Well #3  
201.05R 11/04/68   RE-05       A Control For Pump At Well #3 Elevations, "A-A", West Wall of Utility Tunnel
201.05R 11/04/68   RE-06       A Control For Pump At Well #3: Typical Terminal Cabinet  
201.05R 11/04/68   RE-07       A Addition Of Cabinet Lighting Room B03 Partial Basement Floor Plan Revised
201.05R 12/21/68   RE-08       A Revisions To Darkroom 390 408 Partial Third & Fourth Floor Plans
201.05R 03/04/69   RE-09       A Revisions To Economics Department Area 245, 249, 250 & 251 Partial Second Floor Plan
201.05R 12/21/68   RE-10       A Revisions To Room B13 Partial Basement Floor Plan
201.05R 12/10/68   RE-11       A Revisions To Offices 320 & 322 Partial Third Floor Plan
201.05R 03/25/69   RE-12       A Revision To Rooms 276A, 278A & 285 Partial Second Floor Plan
201.05R 04/10/69   RE-13       A Additional Mechanical Room Lighting Partial Fifth Floor Plan
201.05R 05/14/69   RE-14       A Addition Of Dimming Room 280 Partial Second Floor Plan
201.05R 12/16/69   RE-15       A Revised First Floor Division Head Suite Partial First Floor Plan
201.05R 03/12/68   RM-01       A Condensor Pump No. 4 Part Basement Floor Plan, Piping Diagram
201.05R 03/12/68   RM-02       A Piping For Aninal Cages Room 512 Detail of Plugged Drain, Riser Diagram
201.05R 08/16/68   RM-03       A Addition To Pumped Sewage System Part Basement & Ground Floor Plans 30, 32, 33 & B11
201.05R 10/14/67   RM-04       E Additions & Alterations To Well Water System Partial Riser Piping & Depth Gauge Piping Diagrams. Watertight Sleeve Detail
201.05R 11/05/68   RM-05       A Duct Revisions In Room B-11 Part Basement Plan
201.05R 12/23/68   RM-06       A Duct Revisions In Darkroom 390 & 391 Part Third Floor Plan
201.05R 12/23/68   RM-07       A Duct Revisions & Sink Addition In Darkroom 408 Part Fourth Floor Plan
201.05R 12/23/68   RM-08       A Duct Revisions In Rooms 247 & 251 Part Second Floor Plan
201.05R 01/10/69   RM-09       A Duct Revisions In Room 47 Part Ground Floor Plan
201.05R 02/21/69   RM-10       A CUH Piping Revisions At East Stair Part Basement & Ground Floor Plans
201.05R 03/24/69   RM-11       A Revisions To Air Supply Systems 276, 276A, 278, 278A, 285 & 286  
201.05R 05/08/69   RM-12       A Duct Revisions In Room 409  
201.05R 05/12/69   RM-13       A Addition To Boiler Room Steam Header Elevation of Steam Header Looking North
201.05R 09/12/69   RM-14       A Through Grilles For Toilet Room Vestibules Plan & Section
201.05R 10/20/69   RM-15       E Revised Third Floor President's Suite Linear Diffuser, Linear Wall Grill, Notes, Sections
201.05R 12/17/69   RM-16       E Alterations To A/C System For Division Head, 101, 142 & 143 Notes, Sections
201.05R 09/04/68   RS-01       A Revised Mechanical Room Plan & Section
201.05R 09/16/68   RS-02       A East Alcove Revision Partial Plan, Revised Detail
201.05R 09/24/68   RS-03       A Revision To Detail 6/S22 Elevation. See Detail 6/S-22 For All Additional Data
201.05R 10/04/68   RS-04       A Special Wall Reinforcing, First Floor Wall Elevation, Section X-X
201.05R 10/17/68   RS-05       A Flange Plate Detail Partial Roof Plan, Section
201.05R 10/25/68   RS-06       A Manhole Installation, Well #3 Vicinity & Project Plans, Section
201.05R 11/23/68   RS-07       A Slab Removal Alternate Partial Floor Plan, Sections
201.05R 11/23/68   RS-08       A Revision To South Alcove & D/S-11 South Alcove 2nd& 5th Floor, Connection Detail, Clarification To D/S-11 Per A/21
201.05R 01/24/69   RS-09       A Additional Beam, Fifth Floor South Alcove Partial Plan, Detail
201.05R 11/09/70   RS-10   As-Built   E Weather Station Support System Partial Roof Plan, Pitch Pocket Detail
201.05R 02/18/69   RS-11       A Modified Beam Location, South Stair Plan, Key Plan, Section
201.05R 02/18/69   RS-12       A Modified Column Base, East Penthouse Plan, Sections
201.05R 02/24/68   RS-13       A Relocated Existing Beam At Roof Partial Plan, Detail
201.05R 03/27/69   RS-14       A Concrete Wall Alterations At South Stairs Partial Plan, Section X-X
201.05R 05/05/69   RS-15       A Penthouse Stair Landing Support
201.05R 05/20/69   RS-16       A Addition To Entry Canopy Plan & Elevation